The Hornsby Bend Health & Wellness Center, located at 3700 Gilbert Road (across from Dailey Middle School) will bring expanded clinical services to Hornsby Bend and its surrounding communities. The center will foster mental and physical wellbeing while building community among Eastern Travis County residents.

PROPOSED SERVICES

  • Primary care
  • Integrated behavioral health and oral health assessment
  • Select specialty care services via Telehealth
  • Accessible community gathering space (indoor community room and green space)

To learn more about the future health and wellness center, click here.

WAYS TO GET INVOLVED

2. Click “subscribe” to stay involved and receive frequent project updates.

3. If you live in the Hornsby Bend area and would like to join the Hornsby Bend Health & Wellness Advisory Committee, contact Yesenia Ramos.

4. Schedule an update to your upcoming community advocacy group or neighborhood association meeting. Email Yesenia Ramos.

The Hornsby Bend Health & Wellness Center, located at 3700 Gilbert Road (across from Dailey Middle School) will bring expanded clinical services to Hornsby Bend and its surrounding communities. The center will foster mental and physical wellbeing while building community among Eastern Travis County residents.

PROPOSED SERVICES

  • Primary care
  • Integrated behavioral health and oral health assessment
  • Select specialty care services via Telehealth
  • Accessible community gathering space (indoor community room and green space)

To learn more about the future health and wellness center, click here.

WAYS TO GET INVOLVED

2. Click “subscribe” to stay involved and receive frequent project updates.

3. If you live in the Hornsby Bend area and would like to join the Hornsby Bend Health & Wellness Advisory Committee, contact Yesenia Ramos.

4. Schedule an update to your upcoming community advocacy group or neighborhood association meeting. Email Yesenia Ramos.

  • Update: October 25, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The general contractor, IE2, started construction at the beginning of September. The concrete pour is scheduled for 2 a.m. on Friday, November 4. The reason for the early morning pour is that concrete naturally produces heat as it dries, so pouring the concrete before sunrise allows workers to level the mixture before it gets too hot outside. This will also help avoid dense traffic on Gilbert Rd. as the construction trucks enter and exit the site. Thank you for understanding if bright lights or loud noises occur during this concrete pour.

    We know construction can be disruptive, so we are asking for your patience and understanding throughout the next nine months. We ask that you subscribe for text updates on the construction of the center and the impact to the neighborhood by texting “Hornsby Bend” to 833-382-2226 or "Hornsby Bend ESP" to 833-382-2226 for updates in Spanish.

  • Update: September 23, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Construction has begun on the Hornsby Bend Health & Wellness Center.

    After completing the permitting process, construction began this week on the new health and wellness center in Hornsby Bend, 3700 Gilbert Road (across from Dailey Middle School). Substantial completion of the Hornsby Bend site is expected to be reached by the end of next summer. This facility, which broke ground last spring, is expected to open to patients by fall 2023.

    The Hornsby Bend Health & Wellness Center will offer primary care, integrated behavioral health and oral health assessment, select specialty care via telehealth and an accessible community gathering space. About 21.4% of residents in the region are below 200% FPL, and have a higher rate of asthma, COPD, diabetes, heart failure, hypertension, and renal failure.

    *Please post your questions and comments in the forum and questions sections of this website and subscribe for updates.


  • Update: August 16, 2022

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Central Health received a site development permit late Monday, August 15, 2022. The permit was initially submitted on June 18, 2021. At this time, the general contractor will take over the project to begin formal construction. The general contractor is reviewing and adjusting construction timelines. We will communicate any impacts to the opening of the center.

    While the site development permit was under review, other work began to advance this project:

    • Identification and recording of easements with SouthWest Water Corporation
    • Posting of bond for Storm Water Protection Program with City of Austin
    • Mobilization by general contractor and installation of construction trailer
    • Planning for operational timelines and resources including staffing requirements included in the Fiscal Year 2023 budget
    • Advancement of an accessible playground for community use