Update: August 16, 2022

Central Health received a site development permit late Monday, August 15, 2022. The permit was initially submitted on June 18, 2021. At this time, the general contractor will take over the project to begin formal construction. The general contractor is reviewing and adjusting construction timelines. We will communicate any impacts to the opening of the center.

While the site development permit was under review, other work began to advance this project:

  • Identification and recording of easements with SouthWest Water Corporation
  • Posting of bond for Storm Water Protection Program with City of Austin
  • Mobilization by general contractor and installation of construction trailer
  • Planning for operational timelines and resources including staffing requirements included in the Fiscal Year 2023 budget
  • Advancement of an accessible playground for community use
  • Development of furniture, fixture, and equipment solicitation packages for both sites


Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>